To supply and install 23 off HULK Percussion anchors to a depth of 5m as part of the strengthening of Platform six at Redfern Station NSW.
To supply, install and load test 3 off percussion driven earth anchors (PDEA’s) through a 500mm concrete footing to a depth of 4m. The purpose of the anchors is to strengthen the existing foundation so that a crane can be installed on it.
To supply and Install clusters of earth anchors at various winch sites along the power line build route which provide ballast for the cable and conductor hauling winches.
To supply, install and load test percussion driven earth anchors, wire ropes and tensioning gear at the Rear Main Lead Navigation Aid in Newcastle as a means of stabilising scaffolding used for the refurbishment of the Navigation tower.